On May 22, 2017, the Bharatiya Janata Party (BJP) tweeted it had ratcheted the pace of rural road construction under the Pradhan Mantri Gram Sadak Yojana (PMGSY) to 133 km a day over the three years to 2016-17, up from 69.35 km a day in 2013-14.
However, compared with the Narendra Modi government’s own performance in the first two years, the pace of rural road construction has slackened, connecting, up to January 2017, less than half (46%) of the habitations targeted under PMGSY-I in 2016-17, an IndiaSpend