Hydropower dreams fade on green concerns
Jyoti Mukul & Mansi Taneja / New Delhi Jan 03, 2011, 00:57 IST

India’s hydropower projects are in troubled waters. Once touted as an important engine for power capacity addition, the share of hydropower in total installed generation capacity has hit a historic low of 22 per cent.

And, it is expected to slow down further, as the sector is mired in controversies and technical problems. So much so, the country is set to miss even the revised 11th Plan capacity addition target of 8,237 Mw.

While hydropower, along with nuclear, is regarded as a cleaner source of energy, environmental and social concerns have impacted the sector’s growth, since the projects are invariably located in environmentally fragile regions. With a little over 5,000 Mw added during the five-year period ending March 31, 2012, capacity addition in the sector could be lower than the 7,886 Mw added in the 10th Plan period. At 37,367 Mw, it is currently 22 per cent of the total 167,077 Mw installed capacity.

The country’s biggest hydropower producer, government-owned NHPC, would not be able to meet its 3,000 Mw capacity target for the current Plan, says its chairman, S K Garg. And, the country’s biggest power producer, NTPC, that had hoped to make it big in hydropower projects, has been forced to go slow. “We may not be very aggressive in hydro but we will continue to pursue it,” says NTPC chairman Arup Roychoudhury.

He admits a need to re-examine the strategy for these projects. While NTPC’s 600 Mw Loharinag Pala project in Uttarakhand has been scrapped, with the government declaring a 135-kilometre stretch of the ecologically sensitive Bhagirathi river as India’s first dam-free zone, design problems have delayed its Kol dam project in HP.

Technical, social issues
Besides scrapping of projects in Uttarakhand and Arunachal Pradesh on environmental and religious grounds, faulty designs, technical issues and floods have delayed project construction. The Central Electricity Authority, technical regulator for the power sector, is currently reviewing the targets for the current and the next five-year Plan. “There are some hiccups but we do not anticipate big problems,” says CEA chairman Gurdial Singh.

There has been an emphasis on adding hydropower capacity in the past decade. Especially so in states such as Himachal, Uttarakhand and the northeast, where hydropower is one of the few investment avenues that state governments can offer to industry.

But monitoring of the projects is poor. According to the South Asia Network on Dams, Rivers & People (SANDRP), a network of organisations and individuals working on water issues, the installed capacity of large hydro projects has increased at a compound growth rate of 4.35 per cent annually during 1991-2005, higher than all other power sub-sectors. But there is little attempt at a credible assessment of performance. “Unfortunately, project appraisals—from not only an environment and social but also technical angle—are poor,” says Himanshu Thakkar, convener, SANDRP.

Thakkar notes generation from each installed megawatt has been almost continuously falling over the past 15 years. It was 3.97 million units per Mw of hydropower in 1994-95 but fell around 30 per cent to 2.87 million units in 2009-10. “Unviable projects, over-development, optimistic assumptions, siltation and inadequate maintenance are some of the reasons.”

When a project is given techno-economic clearance, it is based on a promise that it will generate a certain number of units at design level, at 90 per cent dependability level. “Our analysis of all the hydropower projects show 89 per cent of the projects generate at below the design capacity. In fact, 50 per cent of the under-performing projects generate at below 50 per cent of design energy,” says the SANDRP report.

According to Thakkar, a lot of unviable capacity is being put up and society is being made to pay for it. He says there is hardly any proper environment impact assessment and public hearing done before putting up projects. Project developers agree that local resistance can be overcome by following norms. “A certain amount of local resistance is normal but if your approach is transparent, then this issue can be tackled,” says Rahul Kumar, chief financial officer and director, Jaiprakash Associates.

No clear solutions
With large scale submergence of land for creation of storage leading to displacement and protests by locals, state governments are going in for run of the river (ROR) projects. These involve diversion of the river into tunnels and then releasing the water again. During the lean season, such projects are not able to generate enough electricity, since they do not store water.

According to a CEA report, storage schemes provide the necessary regulation to increase power generation during a lean flow period and also provide flood moderation, irrigation and drinking water supply benefits. “ROR projects are generally less economical and result in higher power tariff,” says the report.

During floods or the lean season, when there is less water in the river, a project like the 1,000 Mw Tehri power plant, one of the largest storage-based hydel units, can cause underperformance of projects further downstream especially if they are ROR projects. This defeats the purpose of hydropower projects meeting peaking demand.

New Ipad Application :Business Standard's all new IPad App
Click here to download for free
Arrow Other Stories     
- Markets end flat, weakening rupee weighs
- Rupee tumbles to all-time low of 54.99
- Lanco says power plant to shut down if gas supplies dwindle
- Govt to provide Rs 38,500 cr subsidy to oil cos for Q4 FY12
- India-Pak trade declines 30% to $1.5 bn in Apr-Jan FY12
  Read Business news in 
- Benefits Upto Rs. 2.36 Lakhs on the Fully Loaded TJet Petrol.
- Journey on, We are by Your Side. Click here to know more
- The Best Seller is Also the No. 1 in Mileage. Click here
- One Partnership Endless Possibilities. Click here to know more
- A Brand New Server at a Price That Fits Your Budget. Click here
- Watch The Film Here. Click here to know more..
- 1 billion in saving for Unilever without any tangles.
- Learn How One City is Running on FOOD SCRAPS.
- Helping doctors detect diseases earlier, saving costs & extending lives.
- Which is the best plan for your daughter
- Check out the TRUE COLOURS of your Stocks, Now for FREE!
- One of the leading business schools in the world.Know More
Sorry, comments to this story are closed
Latest Messages
Table for Two
  Now available at Special price
  Rs.280/- Only

  Buy Now
BS POLL
Where do you see Nifty at the end of the year?
  4,500
  5,000
  5,500
Submit
Most Popular
Read
E-Mailed
Commented
   
- Shankar Acharya: The exchange rate: economics bites back
- Nitin Pai: The small-country bullies
- Top pvt life insurers shut 1,500 branches in 2 years
- Piramal Healthcare like Berkshire Hathaway: Piramal
- Piramal Healthcare is like Berkshire Hathaway: Ajay Piramal
 
 More  
New Ipad Application
 Business Standard's all new IPad  App
 Click here to download for free
  Hot Searches  
 
Creamy layer |  Air India |  GAAR |  DRDO  |  Black Widow |  Satyamev Jayate |  Akshaya Tritiya |  Aamir Khan |  IPL |  IVRCL |  Ertiga |  Sarfaesi Act |  Vodafone |  Imagine TV |  Transfer pricing |  Rupee |  Kingfisher Airlines |  Silver |  Provident Fund |  income tax refund |  Budget 2012 |  iPhone |  Reliance Industries |  SEBI |  BSNL |  BSE |  NSE |  Mukesh Ambani |  Anil Ambani |  Infosys |  Pranab Mukherjee |  Sonia Gandhi |  Rahul Gandhi |  New Pension Scheme |  Reliance |  RBI |  GDP |  Gold |  Ratan Tata |  ICICI |  B-School |  Sensex |  Tax calculator |  Home Loan |  Personal Finance |  inflation |  oil prices |  Barack Obama |   
 
  Member Area Write to the Editor RSS Archives Advanced Search
  Subscribe to BS print product BS e-paper Newsletter Portfolio Tracker
  BS Products BS Hindi BS Motoring BS Books
Home | Markets & Investing | Companies & Industry | Banking & Finance | Economy & Policy | Opinion
Life & Leisure | Management & Marketing | Tech World | General News
About Us | Partner With Us | Code of Conduct | Careers | Advertise with us| Terms & Conditions | Disclaimer | Contact Us