"IL&FS Engineering and Construction company has been awarded a contract by RVNL, Kolkata for a value of Rs 299.76 crore towards construction of seven elevated metro stations from sub CBD-1 to Titumir in New Garia-Airport Metro Corridor of Kolkata Metro Line in state of West Bengal," the company said in a BSE filing.
The project has to be completed in three years from the date of issue of letter of acceptance.
More From This Section
The company is already executing two railway contracts for RVNL worth more than Rs 500 crore - one involving construction of a new broad gauge railway line in Kadapa and Nellore districts of Andhra Pradesh.
It said it is executing the other project in Maharashtra which involves doubling of Bhigwan-Mohol section part of Daund-Gulbarga doubling in Solapur district.
The company is also executing Rapid Metro Project, phase II in Gurgaon involving construction of 6.7 km of elevated viaduct and five elevated stations of around Rs 350 crore value.
Earlier the company has executed Rapid Metro's phase I contract worth Rs 259 crore that involved construction of single and double track elevated viaduct, including six station buildings.
Shares of the company closed at Rs 39.80 apiece, up 5.99% from the previous close on the BSE today.