KSK Energy Ventures Limited, a Hyderabad-based power project development company, has commenced steam blowing with respect to the Unit-II (135Mw) of the 540-Mw Wardha Warora Project in Maharasthra.
It is anticipated that the next three to four weeks would witness synchronisation with the Grid and commencement of coal-based power generation for this unit as well, the company said in a filing to the BSE on Monday.
Power generation from the first of the four 135-Mw units has already achieved commencement of power generation during May, and it is anticipated that Unit-III and Unit-IV would achieve completion progress in the next two quarters and commencement of power generation before the end of the year, the company said.
KSK Energy’s scrip is currently trading at Rs 165.25 on the BSE, up 2.26 per cent over the previous close of Rs 161.60.