A consortium of Larsen & Toubro (L&T) and Samsung Heavy Industries Company (SHI) "" Korea's leading shipbuilding, offshore construction and engineering company, has bagged a contract valued to the tune of Rs 2,117 crore ($456 million) from Oil and Natural Gas Corporation (ONGC) for the Vasai East Development project to be executed in a timeframe of two years. |
As consortium partner, L&T will execute jobs worth around Rs 776 crore. The scope for the company includes engineering, procurement, onshore fabrication and transportation of the critical booster and high-pressure compression modules. SHI will execute the balance process platform facility for the project. |
|
Fully assembled and pretested compressor modules for the project will be delivered from L&T's unique modular fabrication facility at Hazira, near Surat, which has recently been expanded to meet the growing needs of the energy sector in the country and abroad. |
|
Larsen is developing over 100 acres of additional facility for a rapid expansion of its Hazira complex. |
|
The Vasai East Development project will be located at approximately 80 km north-west of Mumbai, off India's west coast. It will incorporate new booster compressors and a process facilities platform at BCPA-2. |
|
The project will have oil handling capacity of 4,200 barrels a day, gas processing facility of 12 cubic metres a day and water injection of 47,000 barrels a day. Once commissioned, the project will assist gas production at lower pressure from the existing south Vasai field. |
|
Earlier in December 2005, L&T had won a turnkey project valued at Rs 1,300 crore from ONGC for BCP-B2 booster compressor platform for Vasai field. |
|
|
|