"We feel pained," a bench of Justices Dipak Misra and U U Lalit said while directing the firm to deposit Rs five crore within two weeks and Rs 10 crore in the apex court registry by end of next month to pay back the amount to 38 investors.
"You tell us how will you pay? We will later consider whether interest will be paid to them (investors)," the bench told senior advocate Kapil Sibal who was representing Unitech.
More From This Section
Responding to the query, Sibal said "We appreciate the concern of customers. They can take alternative accomodation. We will pay the rent."
The bench shot back saying, "Will they move from rental to rental? Nothing is moving."
Sibal told the court that there should be some solution to the issue but the bench said, "you deposit the money. You deposit Rs 15 crore first. Let them get the principal amount."
"We direct the appellant (Unitech) to deposit Rs 15 crore in the registry of this court. They will deposit Rs five crore in two weeks and rest amount of Rs 10 crore will be deposited by end of September 2016," the bench said and listed the matter for further hearing on October 4.
During the hearing, a number of investors were present in the courtroom and advocate Brajesh Kumar who was representing some of them told the bench that before the National Consumer Commission, Unitech Ltd had assured that they would hand over the possession of flats which was not cone.
"Now, we want refund of the amount," he said about the Unitech Vista project in sector-70, Gurugram (earlier called Gurgaon).
Another investor told the bench that they had paid money to the firm on time and the company was scheduled to hand over the possession of flats in 2012 but till date, they have not given them the flats.
More than two dozen home buyers of Unitech's housing projects in Noida and Gurgaon had approached the National Consumer Disputes Redressal Commission (NCDRC) after the builder had failed to give them possession of the flats as per schedule.
The consumer forum had asked the real estate firm to refund the money to the home buyers with interest.
The apex court had last month asked the company to deposit an interim penalty of Rs 5 crore with the court registry after the firm challenged the order of the consumer forum which had asked the developer to pay Rs 5 crore penalty to three buyers of its Burgundy project.
The court had said that the penalty deposited with the court will be awarded to the buyers or returned to Unitech, depending on the outcome of the case.