|
The previous deadline expired on July 25. This was the second time in this financial year and the fifth time in a row that the project's tendering process was postponed, since bids were first called in June 2001. |
|
Sipat is the first power project in the country to be executed using the energy-efficient 660 mega-watt super critical technology and marks a change from the 500 mega-watt technology used in such projects so far. |
|
NTPC did not receive any bids for the first phase of the project, for which the earlier deadline had been March 28. |
|
The lack of response from equipment suppliers forced NTPC to reduce the four 660 mega-watt units earlier planned for the first phase to three 660 mega-watt units. |
|
Moreover, the company reverted to the 500 mega-watt technology for the second phase of the Sipat project, which was originally scheduled to be executed using the 660 mega-watt technology. |
|
Instead of having one 660 mega-watt units in the second phase, the company planned to have two 500 mega-watt units. |
|
Subsequently, NTPC floated simultaneous bids for one 660 mega-watt and one 500 mega-watt unit and the bid date was set for July 25. This has now been extended by another six weeks. |
|
In light of the delay witnessed in the Sipat project, NTPC reverted to the 500 mega-watt technology for the second stage of the Kahalgaon project, which was initially scheduled to be implemented on the 660 mega-watt super critical format. |
|
Both NTPC and the power ministry are been keen on state-owned Bharat Heavy Electricals Ltd's (Bhel) participation in the bidding process at Sipat so that the project's cost can be kept under control. |
|
Bhel's core competence is in producing 500 mega-watt sets, it lacks the boiler technology for producing the 660 mega-watt sets. |
|
Bhel has now tied-up with Alstom for boiler technology and is expected to bid for the 660 mega-watt unit. The company did not bid for the project earlier. |
|
Power ministry officials said the energy-efficient 660 mega-watt technology was the technology of the future. |
|
Despite Kahalgaon's reversion to the 500 mega-watt technology, NTPC's Barh super thermal project and the North Karanpura project would be implemented using the 660 mega-watt technology, officials said. |
|
Delayed project |
|
|
|
Sipat is the first power project in the country to be executed using the energy-efficient 660 mega-watt super critical technology and marks a change from the 500 mega-watt technology used in such projects so far The lack of response from equipment suppliers forced NTPC to reduce the four 660 mega-watt units earlier planned for the first phase to three 660 mega-watt units Moreover, the company reverted to the 500 mega-watt technology for the second phase of the Sipat project, which was originally scheduled to be executed using the 660 mega-watt technology |
|