CWG project: HC allows DDA to take Rs 90 cr from Emaar MGF for delay

Image
Press Trust of India New Delhi
Last Updated : Jan 20 2013 | 1:24 AM IST

In a set back to real estate giant Emaar MGF, the builder of Commonwealth Games (CWG) village, the Delhi High Court today allowed the DDA to encash Rs 90 crore, which was deposited by the company as bank guarantee, for not completing the project on time.

In an interim order, Justice Vipin Sanghi said that "the pay order for Rs 90 crore may be encashed (by the DDA)".

The court passed the order on a petition filed by the company seeking to restrain DDA from seizing the bank guarantees of Rs 183 crore as damages for not completing the project on time.

The court, however, said that the rest of the amount of Rs 93 crore, shall not be encashed if it has not been encashed so far.