Five months after the world's sixth-largest airport terminal (Terminal 3 or T3) at New Delhi’s Indira Gandhi International Airport was inaugurated, it is all set to miss its deadline to host domestic carriers for the third time.
Some airlines had announced that their flights will land at and take off from the swanky terminal from October 30. But executives of GMR-controlled Delhi International Airport Ltd today said that the deadline looks difficult, though they are yet to communicate this officially to these airlines.
The executives said there is not enough electricity available to power T3 because the 220-kv sub-station cannot supply uninterrupted power, and the approach road to the airport will see heavy traffic once domestic flights are shifted. T3 needs 250 Mw of power to work without hiccups.
The terminal, which was built at a cost of Rs 12,700 crore and has the capacity to handle 34 million passengers per annum, only does international operations at the moment; it is, as a result, working at the rate of 4.54 million passengers per annum.
Taking a dim view of the postponement, the Civil Aviation Ministry, informed sources said, has called a meeting of all the stakeholders on Monday, including the chairman of Delhi Transco which supplies power to T3.
Another airport source, on the condition of anonymity, confirmed that supply of power has become a stumbling block. “The new sub-station cannot provide the power required to run the airport smoothly. Until and unless that is ensured, it will be very difficult for the airport to cater to the huge number of domestic fliers,” said the source.
This will be the third postponement of the shift. The shift to the new terminal was to happen first by mid-July and then by August-end. That deadline was extended to October 30 as the Civil Aviation Ministry did not want any disturbance to the international tourists and delegations coming for the Commonwealth Games.
DÉJÀ VU | |
Deadline | Reason for deferment More From This Section |
July 31 | Erratic power and water supply |
Aug 27 | Erratic power supply, Commonwealth Games |
Oct 30 | Power supply, traffic congestion |
Analysts said the delay could have cost implications for Delhi International Airport Ltd and these things can only be fixed by making the government agencies more accountable.
“The huge investment in the new terminal cannot be justified by using a small part of the airport just because of electricity problems,” said Centre for Asia Pacific Aviation CEO Kapil Kaul. “Had the company missed the deadline, it would have been fined; but there is no such fine for the agency responsible for supplying power.”
This delay has also impacted the plans of the airport operator to convert the earlier international terminal (Terminal 2) into low-cost international terminal. Terminal 2 is lying unutilized ever since the international operations were shifted to T3. Full-service carriers like Air India, Jet Airways and Kingfisher Airlines, along with their low-cost subsidiaries, JetLite and Kingfisher Red respectively, were supposed to shift to T3 first.
The other low-cost carriers - IndiGo, GoAir and SpiceJet - were to operate from the current domestic terminal (1D) till March next year. Immediately after T3 was inaugurated, Delhi International Airport Ltd had carried out test flights to prove the capability of the airport. On July 14, the earlier date of starting international operations, seven arrivals and departures took place. The next day, the world's biggest passenger aircraft, the Airbus 380, had arrived at the airport for a trial flight - a first for India.