The project aims to augment distribution facilities with increasing demand and reducing electricity distribution losses in Haryana, where rapid industrial development and economic growth have led to a drastic rise of electricity demand.
The loan funds will be utilised for bifurcation and trifurcation of overloaded feeders, construction of new substations, augmentation of existing substations, introduction of Automated Meter Reading, installation of meter pillar boxes and single phase and three face meters, and purchasing of other equipment such as power transformers, current and potential transformers, and vacuum circuit breakers.
The project will be executed by the Uttar Haryana Bijli Vitran Nigam Ltd. (UHBVN) covering the northern part of the state and Dakshin Haryana Bijli Vitran Nigam Ltd. (DHBVN) covering the southern part of the state. The project is expected to be completed by June 2019.