It also directed the secretaries to fix responsibilities for time and cost overruns and take action against those held responsible.
According to information complied by the Ministry of Statistics and Programme Implementation (Mospi), of the 720 central infrastructure projects worth at least Rs 150 crore each, 295 have seen delays. The total project implementation cost for these projects has increased 19.10 per cent compared to the initial estimate of Rs 927,317 crore.
More From This Section
The Cabinet Secretariat also directed that every major milestone for these projects should be entered into Mospi's online monitoring system for projects worth more than Rs 150 crore. Ministries also have to ensure physical and financial progress against these milestones is updated every month.
The government said lack of detailed project planning and slackness in periodical reviews led to delays in many infrastructure projects.