IT investment region in state in a limbo

Image
Jayajit Dash Kolkata/ Bhubaneswar
Last Updated : Jan 20 2013 | 12:26 AM IST

Uncertainty surrounds the proposed IT investment region in Orissa with the state government not showing any resolve to expedite the project.

Though the final report on the region was submitted by IL&FS-Infrastructure Development Corporation (IL&FS-IDC) in July this year, the state government is yet to approve the same.

After the approval of the final project report, the state government needed to submit the same to the Government of India.

The proposed IT investment region (ITIR) in the state is in a limbo due to the slackening demand for IT projects, admitted a top official of the state IT department.

"The state government needs to expedite its process of sending the final report on the ITIR to the Centre. Other states like Gujarat, Andhra Pradesh and Kerala have already submitted the final reports to the Centre on the ITIR", an IL&FS-IDC source told Business Standard.

The IT investment region (ITIR) in Orissa was to be developed on an area of 40 sq km (around 10,000 acres) between Bhubaneswar and Khurda. The ITIR project in the state is expected to be fully operational by 2020.

More From This Section

In the final project report on the ITIR, IL&FS-IDC had included among other things an airport, a global IT training centre, a bio-tech park and a science city spread over 350 acres.

The airport was proposed to be developed on an area of about 2,300 acres close to the site of the Indian Institute of Technology (IIT), Orissa which is being developed over 900 acres of land at Jatni, about 20 km from the city.

The Infocity-II project being developed by the state government on over 600 acres of land at Janla on the outskirts of the city would also be a part of the IT investment region.

The ITIR would be developed in two phases out of which 20 per cent of the investment would be committed for the first phase while the balance 80 per cent of the investment for the project will be in the second phase.

The entire cost of the project was yet to be ascertained. While the Centre was to provide external infrastructure for the project in the form of roads, the onus was on the state government to acquire land for the project.

According to the project plan of IL&FS-IDC, 40 per cent of the area of the ITIR would be earmarked for the processing units of information technology (IT) and ITes sectors (IT enabled services) as well as electronics and hardware manufacturing units.

The remaining 60 per cent of the area in the region would be devoted to the non-processing facilities like research and development centre, technological institutes of national and international repute.

This apart there would be a central business district, an integrated township comprising social infrastructure facilities like schools, hospitals and shopping malls and external infrastructure like roads.