Don’t miss the latest developments in business and finance.

Panna, Mukta Deadlock Costs Rs 1.5 Crore A Day

Image
BUSINESS STANDARD
Last Updated : Jan 28 2013 | 1:08 AM IST

The operatorship issue of the Panna, Mukta and Tapti oil fields is costing the British Gas-Reliance-ONGC consortium a production loss of Rs 1.5 crore per day.

The ouput of gas from the fields, currently at 7.5 million metric standard cubic metres a day, can be increased by 5 million metric standard cubic metres in case the operatorship issue is resolved and the consortium partners invest $300-400 million.

At the prevailing prices of gas in the country, the additional revenue from the increased production would be Rs 1.5 crore, petroleum secretary B K Chaturvedi said today.

Also Read

First Published: Sep 27 2002 | 12:00 AM IST