There has been a five-fold rise in progress of work on DFCC: Adesh Sharma

Q&A with Managing Director, Dedicated Freight Corridor Corporation (DFCC)

Image
Sudheer Pal Singh New Delhi
Last Updated : Jun 18 2016 | 8:21 PM IST
DFCC is among the handful of railway projects where work has been fast-tracked significantly in the past two years. The company’s Managing Director Adesh Sharma discusses the status of the project in an interview with Sudheer Pal Singh. Edited excerpts:
 
What is the current status of the project?
DFCC is now on fast track. Things are moving now at a very high speed compared to earlier years. We have placed contracts worth more than Rs 25,100 crore in the past one year, more than twice the value of contracts placed in previous six years. Also, there has been a five-fold increase in the physical progress of the work. Work is progressing from Khurja to Sonnagar on Eastern DFC and Rewari to Palanpur and from Vadodara to Vaitharna on Western DFC. We have placed 76 per cent of the contracts for civil works, 63 per cent of electrical contracts, and 63 per cent of signaling contracts. We will place orders worth Rs 14,000 crore in the current fiscal.  

What is the progress on the expenditure front?

More From This Section

The total expenditure by DFCC stood at Rs 8,600 crore last fiscal as compared to Rs 2,800 crore in the previous fiscal (2014-15). Thus, there is three-fold improvement in financial progress of the project.The target is Rs 12,500 crore for the current financial year. Of this, Rs 3,500 crore will be spent on land acquisition and the balance Rs 9,000 crore will be spent on contractual payments. The project will be commissioned in phases between March 2018 and December 2019.

What will be the revenue model adopted for DFCC when the project is fully commissioned?
The entire revenue for the freight carried by DFCC will be collected by Indian Railways. The railways will pay us Track Access Charges. These charges will have two components –  a fixed component which will take into account loan repayments and staff expenses and a variable component for actual Operation & Maintenance costs including electrical charges. The track access charges will be defined based on the recommendations of a committee.

How would the cost of operation of DFCC compare with that of Indian Railways network?
Our O&M cost will be at least 40 per cent lower than Indian Railways. This is because the average speed of a train on DFCC would be 70-75 Kmph, three times the speed of a goods train on the railways system. Also, the carrying capacity of a DFCC train would be 13,000 tonne as compared to 5,000 tonne being carried today. For a freight train on the DFCC system, the guaranteed delivery period between Delhi and Mumbai will be less than 24 hours as compared to 2-3 days taken by a goods train. We will be limiting the use of guards in trains by using telemetry systems at the end of trains.

Railways freight traffic has been hit recently due to core sector slowdown. How sure are you of capturing freight volumes?
When DFCC is commissioned, 70 per cent of the goods traffic on railways system will get transferred to DFCC. Also, we will capture a lot of new traffic. DFCC will increase the railways modal share in transport which has come down to 36 per cent from 86 per cent at the time of independence. We will be able to target automobiles and perishable goods traffic which is very low today. A lot of industrial development is taking place on the Western corridor. We plan to have multi modal logistic parks. So, much of the traffic will also come from private freight terminals for which a policy has been finalised. DFCC corridors will also play a major role in decongestion. With every train of DFCC carrying 13,000 tonne of load, 1,300 trucks will go off the road.

How much of the land and the funding requirement for the project has been secured?
We have acquired 88.9 per cent of the total land required for the project. In the earlier alignment, there were problems as large number of structures were requiring dismantling as it was passing through heavily built-up area in Khurja to Saharanpur section where the alignment had to be changed. That land acquisition will now be completed smoothly. Also, there were some problems in acquiring land in two patches in Gujarat and Maharashtra. The issues have now been resolved and the land will be handed over to us by December, 2016. We have also been able to convince the state governments for cost sharing of ROBs which has led to savings of Rs 2,500 crore to Indian Railways and DFC. We have also tied up entire funding requirement for the project from World Bank and JICA.