Under RERA regime, it's shape up or ship out for builders

New law could pose challenges of cost escalation, increased paperwork, fear developers

SC directs real estate firm Unitech to pay back investors Rs 15 crore
Karan ChoudhuryRaghavendra Kamath New Delhi/ Mumbai
Last Updated : Oct 18 2016 | 12:53 AM IST
Reeling from a slowdown in sales and a delivery crunch, the real estate sector is in for a double whammy with the Real Estate (Regulation and Development) Act, 2016, or RERA, feel developers.

Under the Act, cleared by Parliament in March, real estate companies, perceived to be a non-transparent lot, would have to submit a slew of details to a proposed regulator. Violations are likely to attract stringent penalties, which are scaring company owners and even prompting directors on their boards to quit.

From small property dealers to board directors of realty firms — all can face punishments under the provisions of RERA. Players in the sector feel threats are manifold. Smaller builders said they fear some clauses in the Act threaten to wipe out their very existence.

There are also fears of cost escalation as clearances could take longer than usual.

“It will be difficult to adapt for every developer, broker and even buyer. RERA would make business difficult for us,” said R K Arora, chairman, Supertech.

The company has been taken to court by buyers for alleged non-delivery of flats.

Arora added paperwork would also increase for developers. “But for the sector, this is the way forward,” he said.

Working on multiple projects would also be a challenge as the proposed regulator would seek details of previous projects before sanctioning new ones, according to the Act. With the number of non-delivered apartments piling up, companies would need to clear the backlog before launching new projects.

In the National Capital Region itself, delivery of an estimated 159 million sq ft of projects was delayed by two years, said research firm Liases Foras in May this year. Another 164 million sq ft were late by 12 to 23 months.

Developers were also worried about details they would have to submit to the regulator.

Apart from the details of the promoters of the companies, they would have to provide details of current and previous projects, and their status, with reasons if they were pending. Details of pending legal cases would also have to be shared with the authority.

Builders fear all this would escalate costs.

One of the biggest hurdles will be that builders have to put 70 per cent of sales receipts from customers in an escrow account, in the backdrop of many developers diverting funds as they are unable to complete projects.

“We need to keep funds in an escrow account. As we won’t have access to those funds, we would need to borrow from banks. With a lot of court verdicts and regulations, we are seeing ‘stress of doing business’ rather than ‘ease of doing business’,” said Deepak Goradia, managing director, Dosti Realty.

Niranjan Hiranandani, chairman and managing director, Hiranandani Communities, said, “This rule can pose a threat to developers who are already stretched. They could face funding problems.’’

Based on the model Act the Centre had framed, state governments were framing rules. They would also soon constitute regulatory authorities. As a result, business models might have to changed, if developers expect to survive.  “This may require extra time and effort from the developers,” said Samatak Das, chief economist and national director, research, Knight Frank India.

However, what is getting them most jittery are the strict norms that would make surviving difficult.  “Developers will be able to launch project only when they have all approvals. This will imply longer timeline for launches and reduced launches,” said Ankur Dhawan, chief business officer, PropTiger.

Listing out the challenges, Ajay Jain, executive director, investment banking and head of real estate group, Centrum Capital, said a builder can sell only the carpet area, but stamp duty has to be paid on saleable area. “The Act has failed to put sufficient onus on the government authorities that delay necessary permissions.”

Smaller players, who work with 500 sqm or a little more space, would have a hard time clearing all the clauses of the Act, experts said. They believe many might have to shut shop. Property dealers or brokers, who in most cases just show properties, have to be cautious, too. Brokers can only market projects for which they are registered and will have to refrain from over-promising on behalf of the builder, according to the rulebook. Online realty players might also be brought under the ambit of RERA, experts said.

There was, however, a silver lining on the horizon. With stringent rules, RERA had brought the focus back on deliveries.

Developers were now focusing only on completing projects and selling units.

Also, all the projects without completion certificate on the date the legislation became active in a state would have to register with RERA.

Hence, developers were in a hurry to complete delayed projects, trying to avoid being brought under the ambit of the Act.

J C Sharma, vice-chairman, Sobha, said, “With RERA, credible and serious developers will become more responsible and non-serious developers will suffer. When we move from one system to another, there will be some challenges. Things will settle down eventually.’’

RULES PINCH
Developers fear the fresh rules would hurt their business

Registration of projects
  • Promoters must register projects with a regulatory authority before booking or selling apartments
  • Every phase of a project to betreated as a standalone; must be registered separately
  • Every application for completion certificate should have minute details, including past project details, delivery status, pending legal cases of the promoter concerned
  • Developer has to be ready with approval and commencement certificate, sanctioned plan, project details at all times
  • Registration mandatory prior to sale or advertising
Escrow accounts
  • An escrow account has to be maintained by developers for depositing 70% of amount realised for any project from allottees
  • Money in escrow accounts must be used only for land and construction cost
  • Developers will be able to sell units only on carpet area. This will exclude the outer areas
Purview
  • All projects with area more than 500 sqm or eight apartments
  • Real estate agents also covered under the  Act
Sources: Government guidelines, industry