Some National Highway projects under various phases of National Highways Development Projects (NHDP) have been delayed mainly due to land acquisition, utility shifting, non availability of soil/ aggregates, poor performance of contractors, environment/forest/wildlife clearance, ROB & RUB issue with Railways, public agitation for additional facilities, arbitration/contractual disputes with contractors etc.