Don’t miss the latest developments in business and finance.

Bharat Heavy Electricals secures Rs 137 cr order for ESP Package

Image
Capital Market
Last Updated : Apr 16 2018 | 1:50 PM IST

At Ramagundam Super Thermal Power Station

Bharat Heavy Electricals has secured an order for the renovation and modernisation of Electrostatic Percipitators (EPS) at Ramagundam Super Thermal Power Station.

Valued at Rs.137 Crore, the turnkey order envisages carrying out R&M of ESPs of three units of 200 MW each at Ramagundam STPS, Stage-I (3x200 MW) of NTPC. These ESPs have been in operation for more than 25 years.

Renovation and modernisation of these ESPs will not only facilitate the operation of these units for many more years, but will also enable these units to meet the revised emission norms for suspended particulate matter (SPM), notified by the Ministry of Environment, Forest and Climate Change (MOEF & CC) in December, 2015.

BHEL's scope of work in the contract includes design, engineering, manufacture, supply, dismantling, erection, testing and commissioning of the ESPs to bring down the SPM emission within the stipulated levels.

Major equipment for the project will be supplied by BHEL's units located at Ranipet and Bhopal. The execution of the contract on site will also be undertaken by the company's Ranipet unit.

Powered by Capital Market - Live News

Disclaimer: No Business Standard Journalist was involved in creation of this content