For laying the gas pipeline, Right of Use (RoU) has been acquired by GAIL in accordance with the provisions of Petroleum & Minerals Pipeline Act (P&MP) Act, 1962. As per the provisions of the Act, the ownership of land remains with the land owner and subsequent to completion of laying of pipeline, land is restored back to its original condition and handed to the respective land owner. Further, compensation is paid to the respective land owner by the entity authorized for laying of pipeline on account of following:
(i) land compensation @ 10% of prevalent market value of land for using the land for laying pipeline.
(ii) Crop compensation for the crops damaged during construction (actual/presumptive)
(iii) Compensation for trees felled for construction works
(iv) Compensation for miscellaneous/incidental damages
Powered by Capital Market - Live News