Alaknanda Hydro Power Company synchronises 1st unit of 82.50 MW
GVK Power & Infrastructure announced that the 330MW (4x82.50MW) Alaknanda Hydro Power Company, a step down subsidiary of the Company has successfully synchronised its First Unit of 82.50 MW with the grid on 10 April 2015 and is generating at full load.The synchronisation of Second and Third Units with the grid are expected during this month and the last Unit (Fourth) is likely to be commissioned by next month.