In the State of Uttar Pradesh there are 60 National Highways with total length of 8483 Kms

Image
Capital Market
Last Updated : Jun 10 2016 | 2:47 PM IST

Status of National Highway Projects in Uttar Pradesh

In the State of Uttar Pradesh there are 60 National Highways with total length of 8483 Kms, out of which 4529 Kms are with NHAI and 3143 Kms with State PWD. NOC is awaited for 10 Nos NHs with 811 Kms.

8 Major Projects having a length of 865 Kms amounting to Rs. 6218 Crs were completed in the past 2 years.

31 Major Projects are ongoing with a total length of 2156 Kms with total TPC of Rs. 19,436 Crs.

24 Major Projects were awarded during 2014-15 & 2015-16, with a total length of 1293 Kms and total TPC of Rs. 16,949 Crs

15 projects are likely to be awarded in the next 12 months with a length of 840 Kms with TPC of Rs.6790 Crs.

1400 Kms of National Highways are under DPR and Civil construction work likely to be awarded in the next two years for approx cost of Rs. 14,000 Crs.

More From This Section

Under CRF and ISC Schemes a total number of 79 Projects have been sanctioned amounting to Rs. 3035 Crs during 2015-16 & 2016-17.

10 Number of new National Highways in the Uttar Pradesh state have been declared with a length of 811 Kms. (DPR invited by the Ministry)

35 Nos of NHs with 2591 Kms length have been approved ' in-principle ', MORTH shall invest an amount of approximately Rs. 25,910 Crs to develop these National Highways, subject to the outcome of DPR / receipt of NOC from the State Govt

In totality, MORTH, through NHAI and State PWD, shall invest approximately an amount of Rs. 74,794 Crs in the State in next two years.

The details of the above projects can be seen in the 13 tables that follow

Table 1 : Details of NHS in Uttar Pradesh

S. No.

Details of NH

Length (Km)i.

Total NH length (60 nos including newly declared NH)

8483 ii.

NH length entrusted to NHAI

4529iii.

NH length entrusted to PWD

3143 iv.

Length of newly declared NHs but NOC from State PWD yet to be received (10 nos )

811 v.

Length of 'In Principle' approved National Highways. (35 nos)

2591vi

Total length

11,074 Km

Table 2: Density of NHs

Sl. No.

NH density in respect of population and area

NH densityUttar Pradesh All India(i)

Length (in Km./1000 Sq Km of area)

34.87 (Area=243286 Sq Km) 28.25 (Area=3287263 Sq Km)(ii)

Length (in Km./Lakh of population) (As per 2011 Census)

4.25 (Population=1996 Lakh) 7.67 (Population=12102 Lakh)

Table 3: Lane distribution of entrusted NHs [7672 Km = 8483 - 811]

S.no

Lane Distribution

% age i.

4 Lane and above

28%ii.

2 Lane

69%iii.

Less than 2 Lane

3%

Table 4: Details Of NH Works In The State Of Uttar Pradesh

S.No.

Programme / Plan

Total No. of Projects Length in Kms Total cost in Crores1

Projects Awarded in 2014-15 & 2015-16

24 1293.29 16948.812

Projects completed during last 2 years

8 864.97 6217.39

Ongoing Major Projects

31 2156.87 19436.422

Projects in pipeline

15 839.72 6789.823

DPR under preparation

1400 140004

CRF & ISC likely to be awarded during 2016-17

79 1706.65 30355

New National Highways Declared

10 811 81106

National Highways declared "In Principle"

35 2591 25910

Total Estimated / Projected investment in UP since May 2014.

8641.66 74793.63

Table 5: Major projects completed during last 2 years. Major Projects costing > Rs.100 Crs.

Sl. No. NH Work Mode Length
TPC/ Civil Cost (Rs. In Cr) Remark/Substantial completion 1 24B 4-laning of Lucknow-Raebareilly section BOT (Annuity) 70 635 Completed in Jan, 20152 93 2 Laning with Paved Shoulder of Agra - Aligarh Section BOT (Toll) 81.4 250 COD for 81.4 km issued in Aug, 20153 24 4 laning of Moradabad - Bareilly BOT (Toll) 121 1267 COD for 118.8 km issued in Nov, 20154 93 4/6 laning of Ghaziabad - Aligarh BOT (Toll) 126.3 1141 COD for 103.89 km issued in June, 20155 25 Unnao ROB and approaches of Lucknow Kanpur section EPC 16.2 53.52 ROB completed and opened for traffic on 23, June, 20156 86 2 laning with paved shoulder of Kanpur - Kabrai Section BOT (Toll) 123.86 373.47 COD for 123.86 km issued in July, 20157 2 6-laning of Etawah - Chakeri section BOT (Toll) mode BOT (Toll) 160.21 1928 6-laning completed for 159.71 km in Sept, 15 8 231 2laning with PS of Raebareilly - Jaunpur on BOT Annuity mode. BOT (Annuity) 166 569.4 Completed in Feb, 2016

Total

864.97 6217.39

TPC: Total Project Cost

COD: Commercial Operation Date.

Table 6 : Ongoing Major Projects: Physical and Financial progress

(a) Projects under NHAI

Sl. No.

NH No. Work Length (km) TPC/ Civil Cost (Rs. Crore) Date of Start Stipulated Date of Completion Status (Present physical progress)1 25 Jajmau Ganga Bridge to Rama Devi Crossing 5.46 201.66 Dec, 05 Dec, 08 94% in Progress2 2&3 Construction of new 4 Lane Agra Bypass(EPC) 32.2 465.5 Jul, 11 Jul, 14 85% in progress3 24 4-laining of Moradabad - Bareilly Section on BOT (Toll) mode 121 1267 Dec,10 June,13 98.6% in progress. (PCOD issued for length of 118.820 km.) Only 1.7 km remains to be completed. Delay to LA problem.4 24 4-laning of Bareilly - Sitapur sec on BOT (Toll) mode 151.2 1046 March, 11 Aug, 13 44% in Progress5 2 6-laning of Etawah - Chakeri section BOT (Toll) mode 160.21 1573 Mar, 13 Sep, 15 99% (6-laning work is completed and balance work viz service road, drains etc at few locations left due to slow progress in LA award)6 91 Ghaziabad to Aligarh (Km 23.600 to Km 140.200) BOT (Toll) mode 126.30 1141 Feb, 11 Aug, 13 96%(PCOD issued for length 103.89km on 23.06.15 7 24B 2-laning with PS of Rbly - Allahabad section on BOT (Toll) mode 106.6 291.4 Jul, 12 Jan, 14 58% in progress8 2 6-laning of Delhi - Agra section on BOT (Toll) mode 179.5 1928 Oct, 12 Apr, 15 51% in progress9 232 2laning with PS of Tanda - Raebareilly on EPC Mode. 155 636 Apr, 14 Oct, 16 70% in progress10 232 2laning with PS of Raebareilly - Banda on EPC Mode. 133 429 Apr, 14 Oct, 16 58% in progress11 56,29 4-lane Varanasi Bypass (Phase-I) on EPC Mode. 16.55

261.00 May, 15 May, 17 20% in progress12 233 4-laning of Ghaghra Bridge to Varanasi section from km 121.800 to km 180.420 [Package-I] on EPC mode. 58.64 674.34 Dec,15 May, 18 The contractor is mobilizing at the site and establishing camps and creating infrastructure to undertake the project.13 233 4-laning of Ghaghra Bridge to Varanasi section of NH-233 from km 180.420 to km 240.340 [Package-II on EPC mode. 59.95 741 Jan, 16 June, 18 The contractor is mobilizing at the site and establishing camps and creating infrastructure to undertake the project.14 233 4-laning of Ghaghra Bridge to Varanasi section of NH-233 from km 240.340 to km 299.350 [Package-III] on EPC mode. 59.07 785 Jan, 16 June, 18 The contractor is mobilizing at the site and establishing camps and creating infrastructure to undertake the project.15 56 4-laning of Sultanpur to Varanasi section of NH-56 from km 134.700 (design chainage km 134.700) to km 205.000 (desing chainage km 209.230) [Package-I] on EPC mode. 74.53 986 Jan, 16 June, 18 The contractor is mobilizing at the site and establishing camps and creating infrastructure to undertake the project.16 56 4-laning of Sultanpur to Varanasi section of NH-56 from km 205.000 (desing chainage km 209.230) to km 263.000 (design chainage 272.590) [Package-II] on EPC mode. 63.36 806 Jan, 16 June, 18 The contractor is mobilizing at the site and establishing camps and creating infrastructure to undertake the project. Total 1502.57 13231.9

(b) Projects under NHDP IV Zone of MORT&H

Sl. No. NH. No. Name of Project Length (Km) Agreement amount (Rs. In cr.) TPC in Crs Date of start Length Completed till March 2016 (km) Stipulated Date of Completion Status (Present physical progress)1 29E Gorakhpur-Ferenda-Nautanwa-Sonouli section 81.41 441.00 569.34 19.03.15 45 Mar, 2017 50%2 28C Barabanki to junction with MDR-13 near Jarwal section 43.00 272.70 358.47 19.03.15 31 Mar, 2017 68%3 28C Junction with MDR-13 near Jarwal to Bahraich bypass section 50.00 261.00 337.58 28.10.14 50 April, 2016 99%4 28C Bahraich bypass to Rupaidiha section 51.00 328.45 437.92 30.10.14 50 June, 2016 90%5 233 Indo-Nepal Border to Rudhauli section 65.87 393.08 551.48 26.06.15 0 June, 2017 5%6 233 Rudhauli to Ghagra Bridge section 56.40 397.50 550.93 25.03.17 30 Mar, 2017 25%7 27 Allahabad to UP/MP Border section 41.72 400.05 774.57 Yet to start 0 - -8 29E Gorakhpur bypass from existing km 79.670 of NH-29E to existing km 251.700 of NH-28 18.25 531.00 531.00 Yet to start 0 - - 407.65 3024.78 4111.29 206

(c) Projects under Uttar Pradesh PWD & PIU of MORT&H

Sl. No NH No. Name of work Length (km.) Sanction Cost ( Rs. Cr.) Date of Start Stipulated Date of Completion Status (Physical completion / likely completion by )1 96 Strengthening with provision of paved shoulder in km. 0.00 to 46.470 of NH-96(330) EPC MODE 46.47 227.74 23-2-13 May, 2016 92% / October, 20162 730 Widening & strengthening from km. 505.00 to 538.00 of NH-730 (EPC MODE). 33.00 207.88 29-2-16 Aug, 2017 Agreement signed on 15-5-15, Appointed date 29-2-2016. 3 730 Widening & strengthening from km. 454.00 to 470.90, 474.00 to 484.00 of NH-730 EPC MODE 26.90 138.44 03-2-16 Feb, 2018 Agreement signed on 13-8-15, Appointed date 03-2-2016 4 730A Widening to two lane carriageway with paved shoulder and strengthening from Km.0.00 to 50.675 of NH-730A (EPC mode) 50.675 164.54 28-2-14 Dec, 2016 35%/ Dec, 2016 - Notice for imposing LD issued. 5 Eastern side of NH-24B Construction of Ring Road for Raebareli city (Phase-I) on Eastern Side of NH-24B 17.93 302.73 04.03.2014 July,2017 The contractor has promised to complete the work by 31.07.2017.6 56 Four laning of Babatpur-Varanasi section of NH-56 (231) Km 263.00 to 280.25 (EPC MODE) 17.25 753.57 15-9-15 Sept, 2017 Physical progress is 11.25%. Likely date of completion September, 2017.7 730A Widening to two lane with paved shoulder from Km.51.000 (50.675) to 105.500 of NH-730A on EPC mode 54.43 298.33 Yet to start - LOA issued on 16-5-2016. Agreement yet to be signed and appointed date to be notified. Total 246.655 2093.23

Table 7 : Projects awarded in 2014-15 & 2015-16:

Sl No Name of the Project Length (km) Cost (TPC in Crore)NH(O) Projects executed by State PWD1

Widening with Paved shoulders & Strengthening from Km.0.00 to 50.675 of NH-730A EPC MODE

50.675 164.542

Strengthening with provision of paved shoulder in km. 0.00 to 46.470 of NH-96(330) EPC MODE

46.47 227.743

Widening & strengthening from km.505.00 to 538.00 of NH-730 (EPC MODE)

33.00 207.884

Widening & strengthening from km. 454.00 to 470.90, 474.00 to 484.00 of NH-730 EPC MODE

26.90 138.445

Constn. for four laning of Babatpur-Varanasi section of NH-56 (231) Km 263.00 to 280.25 (EPC MODE)

17.25 753.576

Construction of Ring Road for Raebareli City (Phase -I) on Eastern side of NH 24B

17.927 302.737

Widening to two lane with paved shoulder from Km.51.000 (50.675) to 105.500 of NH-730A on EPC mode

54.43 298.33

Sub-total A

246.652 2093.23NHDP-IV executed by state PWD8

Barabanki to junction with MDR 13 near Jarwal section of NH-28C in Uttar Pradesh km 0 to 43

42.45 358.479

Junction with MDR-13 near Jarwal to Bahraich section of NH-28C in Uttar Pradesh km 43 to 93

50.49 337.5810

Bahraich bypass to Rupaidha section NH-28C in Uttar Pradesh km 99 to150

53.85 437.9211

Sonouli to Gorakhpur section of NH-29E in Uttar Pradesh km 0/0 to 80/0

81.412 569.3412

Indo-Nepal Border to Rudhauli section of NH-233 in Uttar Pradesh km 0/0 to 65/870

65.87 551.4813

Rudhauli to Ghagra Bridge section of NH-233 in Uttar Pradesh km 65/870 to 122/270

54.36 550.9314

Four laning of Allahabad to UP/MP Border section of NH-27

41.34 774.5715

Gorakhpur bypass from existing km 79.670 of NH-29E to existing km 251.700 of NH-28

18.25 531

Sub-total B

408.022 4111.29NHDP-IV executed by NHAI16

Construction of 4-lane Varanasi Bypass connecting NH-29 and NH-56 (Phase-I) on EPC Mode.

16.550 261.0017

4-laning of Ghaghara Bridge to Varanasi section from km 121.800 to km 180.420 (Pkg-I) on EPC Mode.

58.635 674.3418

4-laning of Ghaghara Bridge to Varanasi section from km 180.420 to km 240.340 (Pkg-II) on EPC Mode.

59.947 741.0019

4-laning of Ghaghara Bridge to Varanasi section from km 240.340 to km 299.350 (Pkg-III) on EPC Mode.

59.070 785.0020

6 laning of Agra to Etawah Bypass section from km 199.660 to km 323.525 on BOT (Toll)

124.520 1650.2021

4-laning of Sultanpur to Varanasi section of NH-56 from km 134.700 to km 205.000 (Design Ch. 209.230) (PKG-1) on EPC Mode.

74.53 986.00022

4-laning of Sultanpur to Varanasi section of NH-56 from km km 205.000 to km 263.000 (Design Ch. 272.590) (PKG-2) on EPC Mode.

63.36 806.00023

6-lane Eastern Peripheral Expressway around Delhi

135 3991.4324

Construction of Delhi - Meerut Expressway

45 849.32

Sub-total C

636.612 10744.29

Total (A+B+C)

1293.29 16948.81

Table 8: Projects in pipeline:

Sl No Name of the Project Length (km) Cost (TPC in Crore)NH(O) Projects executed by State PWD1

Widening of existing single lane carriageway to two lane carriageway with paved shoulder and strengthening from Km.51.000 (50.675) to 105.000 of NH-730A

54.43 298.332

Rehabilitation and Up-gradation of Bahraich-Shrawasti section (Km.248.40 to 310.00) of NH-730 in the State of Uttar Pradesh to two lanes with paved shoulder on EPC mode

61.90 388.833

Rehabilitation and Up-gradation of Harpalpur - Sugira section (Km.89.600 to 133.520) of NH-76 (New NH No.339) in the State of Uttar Pradesh to two lane with paved shoulder under EPC mode

41.47 208.504

Rehabilitation and Up-gradation of from Km.285.000 to 326.000 of NH-76 (Kalupur-Lalata road) to two lane with paved shoulder on EPC mode in the State of Uttar Pradesh

41.25 240.305

Rehabilitation and Up-gradation of Lakhimpur -Sisiya section (Km.140.00 to 188.80) of NH-730 to two lanes with paved shoulder on EPC mode in the State of Uttar Pradesh

48.80 296.506

Rehabilitation and Up-gradation of Sultanpur - Pratapgarh section of NH-96 from existing km 60/000 to km 90/000 [Design Ch. 60.000 to Ch. 90.865] to Two lane with paved shoulders on EPC mode in the state of Uttar Pradesh

30.87 208.887

Rehabilitation and Up-gradation of Tulsipur- Barhani Section (Km 351+000 to Km 385+000) of NH-730 to two lane with paved shoulder under EPC mode in the State of Uttar Pradesh

34.00 249.508

Rehabilitation and Up-gradation of Sisiya-Nanpara section (Km.188.8 to 226.100) of NH-730 in the State of Uttar Pradesh to two lanes with paved shoulder under EPC mode

37.46 213.519

Rehabilitation and Up-gradation of Pratapgarh to Allahabad Bypass road junction section of NH-96 from existing km 100+800 to km 135+230 [Design Ch.100+800 to Ch. 135+500] to four lanes with paved shoulders on EPC mode in the state of Uttar Pradesh

34.70 599.3410

Rehabilitation and Up-gradation of Puranpur - Khutar section (Km38.000 to 82.000) of NH-730 in the State of Uttar Pradesh to two lanes with paved shoulder under EPC mode

44.13 225.96

Sub-total A

429.01 2929.6511

Aligarh-Moradabad

146.37 503.3412

Meerut - Buldandshar

61.19 609.7213

Varansi-Gorakhpur (Pkg-II)

72.15 856.6414

Varansi-Gorakhpur (Pkg-III)

65.38 852.3215

Varansi-Gorakhpur (Pkg-IV)

65.62 1038.15

Sub-total A

410.71 3860.17

TOTAL

839.72 6789.82

Table 9 :DPR Under Preparation:

Sl No

Name of the Project

Length (km) Cost (TPC in Crore)NH(O) Projects executed by State PWD1 DPR of remaining stretches of NH-76, NH-730, NH-330A, NH-19, NH-119 700 7000NHDP-IV executed by NHAI2

4-laning of Aligarh-Kanpur section of NH-91 under NHDP Phase-IV on BOT (Toll) mode

282 km 3

Lucknow Ring Road under NHDP Phase-VII

100 km 4

Varanasi Ring Road (Phase-II) under Phase-VII

43 km 5

2-laning with paved shoulders of Varanasi-Hanumanha section of NH-7 under NHDP Phase-IV on EPC mode

125 km 6

6-laning of Hapur bypass-Moradabad section of NH-24 under NHDP phase-V

100 km 7

2-laning with paved shoulders of Unnao-Lalganj section of NH-232A under NHDP Phase-IV on BOT (Annuity) mode

50 km 700 7000

Total

1400 14000

Table 10 : List of CRF works:

Sl No

Name of the proposal

Length in Km. Modified cost by Ministry1.

Widening and strengthening OF Kairana-Khatauli road from Km.33.000 to 47.900 (MDR)

14.90 28.312.

Bhitaura- bahedi road (ODR) from Km 1.000 to 42.800, comprising of widening and strengthening work from 3.75 m to 7 m (two laning).

41.80 77.933.

Sishgarh-bahedi road(ODR) from km 1 to 20, comprising of widening and strengthening work from 3.75 m to 7 m (two laning)

20.00 36.684

Widening and strengthening of Baha-Udi road from Km.22 to 30

9.000 18.835

Widening and strengthening of Udi-Chakarnagar-Bareh road

42.300 94.406

Widening and strengthening of Barkheda-Daolatpur-Uganpur-Suhas road from Km 0.000 to 20.650

20.650 48.087

Strengthening of Gawan -Anupshahar road from Km 0.000 to 9.390

9.390 12.248

Widening and strengthening of Widening & Strengthening of Babrala-Anupshahar road from Km 0.00 to Km 16.630

16.630 14.489

Widening & Strengthening of Rajpura-Tikata-Bahjoi road from Km 0.00 to 24.800

24.800 36.3210

Widening & Strengthening of link road connecting Km 193 of NH-93 (Chandausi) via Ata-Mauassu-Naglia ballu-Tharaisa Jai Singh up to Pawasa from Km 0.00 to 17.00

17.000 26.7511

Widening & Strengthening of road connecting Km 158 of Meerut Badaun road to Mithunpur via Ghonsli raja (Km 0.00 to Km 11.850)

11.850 20.1412

Widening & Strengthening of link road from Sahaswan Nadha to Pathakpur via Ghari Khanpur from Km. 0.00 to 8.000

8.000 14.8413

Widening & Strengthening of Kanth - Mishripur - Begampur - Karanpur - Rattupura - Thakurdwara - Jaspur Road (KMBK road from Km 0.000 to 13.600, KRSJ road from Km1.000 to 8.000, TR road from Km 1.000 to 8.000 and TJ road from Km 0.000 to 5.000).

33.700 67.8014

Widening & Strengthening of Dalpatpur - Aliganj from Km 0.000 to 42.000

42.000 64.2715

Widening & Strengthening of Bisalpur - Bilsanda Gola road from Km 1.580to 21.000.

19.580 21.7816

Widening & Strengthening of Nawabganj - Dalelnagar- Vaharjagit- Barkheda road ( Barkheda-Nawabganj road) from Km 16.000 to 19.750

3.750 10.0217

Widening of Bisauli- Aonla road from Km.0.000 to 14.000

14.000 12.3918

Widening & Strengthening from Gandinagar Jamo road to Jodhnapur Madka via Barouliya

6.575 8.6419

Strengthening of Jais - Mohanganj road from Km 0.000 to 17.000

17.000 22.5720

Strengthening of road from Varisganj to Devkali Chauraha via Raniganj from Km 0.000 to 10.000) ( Varisganj-Shukulbazar-Subeha road)

10.000 11.0921

Strengthening from road Km 2 of Sourikh-Daulatabad road to Behatarampur -Kairda Vishungad road (Km 0.00 to 10.00)

10.000 20.9322

Widening & Strengthening of Raebareli-Gurubakshganj-Kheri-Semri road from Km 5.800 to Km to 42.300

36.500 68.5223

Widening & Strengthening of Lalganj-Semarpaha-Ralpur road Km 7.00 to 19.600

12.600 19.7324

Widening & Strengthening of remaining portion of Raebareli-Dalmau-Fatehpur road (Km 0.00 to Km 2.953)

2.953 3.1225

Widening & Strengthening of Dalmau-Jagatpur road from Km 3.600 to Km 26.000

22.400 35.6526

Widening & Strengthening of Jahanabad Richa road from Km. 0.00 to 10.000

10.000 14.6227

Widening & Strengthening of Puranpur Diyoriya Kalan road from Km. 30.00 to 44.720)

14.720 33.0328

Widening & Strengthening of Bareilly Bisalpur road from Km 26.000 to Km 40.800

14.800 27.9729

Strengthening of Bilraya-Panwari road from Km 288.00 to Km 311.650

23.650 36.5330

Strengthening of Muradganj-Ayana-Bijhalpur road (Km 0.00 to 10.00)

13.700 26.3931

Widening & Strengthening of Biswan-Laharpur-Hargaon road from Km 0.000 to Km 27.200

27.200 56.6832

Widening & Strengthening of Biswa - Mahmuda road from Km 0.000 to 24.830

24.830 56.3933

Widening & Strengthening of Lalitpur - Mehrauni road from Km 5.360 to 21.000 and from Km 35.500 to 42.000

22.140 41.4834

Widening & Strengthening of Jhansi-Unnao-Balaji road from Km 0.000 to 10.900, which starts from Km 5 of NH-75

10.900 18.6235

Widening & Strengthening of Jalalpur- Rampur -Bhagan- Tarun Aahirouli road from Km 0.000 to 22.350

22.350 37.1136

Widening & Strengthening of Bisalpur Banda Puwayan Khutar road from Km 21.000 to 32.200

11.20 22.6737

Widening & Strengthening of Amroha ring road / bypass from Km 0.00 to Km 35.775

35.775 53.5238

Widening & Strengthening of Chunahar Jamui Aaharora road from Km 1.00 to 20.325

19.025 43.6539

Widening and strengthening of Nawabganj - Dalelnagar-Baherjageer road from Km 0.000 to 16.000

16.000 27.8240

Widening and strengthening of Inayatpur - Ghopa (Fulaona) link road

12.200 10.4741

Widening and strengthening of Birsingh - Halapur link road

17.050 18.9042

Widening and strengthening of road in Lambua via Kothra Hagiganj, Rajumari to Tatomureni from Km. 0.00 to 15.500

15.500 23.6043

Widening and Strengthening from Aligarh Ramghat road to Gaonkheda Godha CTK road from Km 0.00 to Km 15.300

15.300 29.4444

Strengthening & widening of Vidhnu-Kisan Nagar Nehar Patri road from Km 1.000 to 18.600

17.600 24.6745

Wideing and Strengthening of Chibramau-Kairda road Km.0.000 to 9.800

9.800 21.2646

Widening and Strengthening of Lalitpur - Devgarh road from Km 0.000 to 32.300

32.300 53.7747

Widening and Strengthening of Jakhora - Rajghat road from Km 0.000 to 19.000

19.000 35.3148

Widening and Strengthening of Lalitpur - Rajghat road from Km 0.000 to 21.560

21.560 37.8249

Widening and Strengthening of Karahi to Pathra via Goura-Tigodwa from Km 0.000 to 9.000

9.00 4.1350

Widening and Strengthening of Baansi Ganguli Chauraha to Gothwa Ghat via Piperhiya from Km 0.000 to 5.000

5.000 2.3651

Strengthening of Chilaha- Gopiganj road Km 0.00 to 10.40

10.400 14.3152

Widening & Strengthening of link road connecting NH-509 at Narora via Jamuna singh road-Ishampur-Asadpur-Dabathra with State Road 18 (Junawa) (Km 0.00 to 13.100)

13.100 23.9453

Widening and Strengthening of Gorakhpur- Pipraich- Kaptanganj road from Km 0.000 to 19.485

19.485 36.7854

Widening and Strengthening of Sahajanwan - Bakhira road from Km 0.000 to 23.200

23.200 60.0255

Pipiganj - Jasval - Sisai - Sahjanwan road from Km 0.000 to 20.200

20.200 28.3656

Four laning of interna lportion of old NH-2 from Km 161.800 to 180.000 (Kokhraj to Manauri)

18.200 127.3257

Strengthening of city protionof old NH-93 handed over to State PWD from Umed to Nagla Bhus from Km 0.000 to 10.635

10.635 20.8658

Widening and Strengthening of Agra-Jalesar-Sikandramau road from Km 62.000 to 74.4000

10.700 18.0659

Widening and Strengthening of Bhojubir-Sindhora road from Km 2.00 to 23.200

21.200 46.7760

Widening and Strengthening of link road connecting NH-11 to NH-2 at (Achnera Deen Dayal Dham Farah road)
20.925 41.4461

Widening & Strengthening of Mau to Mohmmadabad road via Yousufpur (Km 0.00 to Km 10.000)

10.000 24.7062

Widening of BTIB to Mahowa Dhobha Shahapur road (Km 0.000 to Km 18.000

18.000 27.2563

Widening & Strengthening of Shoharatgarh to Palta Devi lin road via Ramwapur Chouraha

5.000 2.1264

Widening & Strengthening of Jaunpur-Malhani-Khuthan road (Km 0.00 to Km 27.150)

27.150 32.0265

Widening & Strengthening of Kundaha-Sujanganj-MachliShehar-Madiyahoo-Jalalpur-Kerakat-Sultanpur road (Km 0.00 to 27.080 & Km 87.500 to 96.200)

36.080 45.9866

Widening & Strengthening of Jivli -Devgaon -Mehnajpur -Aodiyar road (Km 18.440 to Km 33.500)

15.060 15.2367

Widening & Strengthening of road from Babatpur-Chaubepur-Bhagtua-Balua bridge (Km. 32.340 to 61.13)

39.350 93.2868

Widening & Strengthening of Baburi-Dharauli road (Km 0.00 to 15.00)

15.000 34.6069

Widening & Strengthening of Chahaniya-Dhanapur-Mahuji-Jamaniya road

42.000 76.5970

Widening & Strengthening of Lalapur Imliya Kanjasa Bhita road (Km 0.00 to Km 23.600)

23.600 32.6671

Widening & Strengthening of Pailani-Galauli-Bara road (Km 0.00 to 15.00)

15.000 27.5272

Widening & Strengthening of Kaptanganj-Siswan-Nichlaul-Thuthiwari-Nautanwa

73.000 189.8973

Widening & Strengthening of Aligarh to Gonda road (Km 0.00 to Km 18.200

16.200 27.0174

Widening & Strengthening of Gazi ka bagh Mubarakpur link road (Km 0.00 to Km 13.600)

13.600 17.9775

Widening & Strengthening of SMK road to lutar khaur bhaiyya Laxman ka Pura-Meja-Bhatauti road (Km 0.000 to Km 19.250)

19.25 44.5476

Widening & Strengthening Delhupur-Raniganj-Patti Kohdaur road (Km 0.000 to Km 61.000)

61.00 117.64

Sub-total

1505.313 2780.58

ISC Works

1

Widening of existing single lane carriageway to two lanes with Strengthening from Km.0.00 to Km 49.00of LalganjHaliyaAndawaManigaraha Road (ODR) upto Madhya Pradesh Border

49.00 98.972

Widening of existing single lane carriageway to two lanes Km. 2.50 to Km 36.24 and with two lane paved shoulder from Km. 0.00 to Km 2.50 with Strengthening from Km.0.00 to Km 36.24 of Chopan to MP Border Road (ODR)

36.24 96.053

Widening of existing carriageway to two lanes with paved shoulder with Strengthening from Km.0.00 to Km 15.43 of BhabniPokharaAasandeeh Road (ODR) of Distt. Sonebhadrain

15.43 59.42

Sub-total

100.67 254.44

Total

1706.653 3035

Table 11: New National Highways Declared

S N

NH No

Name of Highway

Length in Km

Dateof Declaration

1

123

Dholpur to Bharatpur 15

13.8.2011

2

330

Allahabad-Pratapgarh-Sultanpur-Faizabad-Ayodhya-Nawabganj-Gonda-terminating at NH-730 near Balrampur (Portion from Ayodhya to Balramapur via Gonda) 96

31-07-2013

3

334A

Purkaji - Laksar - Haridwar road 15

26.02.2014

4

334B New

Meerut - Haryana Border 60

04.03.2014

5

219 New

Bihar Border- Chandauli (NH-19) 5

04.03.2014

6

709A

Haryana Border- Shamli- Budhana- Meerut (NH-34) 94

10.03.2015

7

727A

Gorakhpur (NH-27)- Deoria- Salempur- Bihar Border 100

10.03.2015

8

227A

Ayodhya (NH-27)- Chhawni- Kalwadi- Barhalganj- Barhaj- Bihar Border 218

10.03.2015

9

731A

Near Pratapgarh (NH-31)- Jethwada- Shrangverpur- Manjhanpur- Rajapur- Near Chitrakoot (NH-35) 160

10.03.2015

10

330B

Near Gonda (NH-330)- Near Jaewal (NH-927) 48

10.03.2015

TOTAL

811

Table 12 : National Highways declared 'In Principle':

Sl. No.

Name of Highway / road

Length in U.P. (in Kms)

1

Allahabad-Jaunpur-Gorakhpur

170.00

2

Panipat- Haryan / UP border - Shamli-Muzaffarnagar-Bijnor-Nagina

131.00

3

Delhi- Saharanpur

170.00

4

Ghaziabad-Noida-Faridabad-Sohna (Total length= 75 km; Haryana= 57 km; UP= 18 km)

18.00

5

Nuh-Mandkola-Palwal-Jewar-Bulandshahar (Total length= 60 km; Haryana= 52 km; UP= 8 km)

8.00

6

Palwal-Aligarh (Total length= 83 km; Haryana= 17 km; UP= 66 km)

66.007

Faridabad (Kheri Bridge)-Jasana-Cheersi-Manjhawali-Atta Gujaran-Dankor-Yamuna Expressway (Total length= 25 km; Haryana= 17 km; UP= 8 km)

8.008

Guna- Ashok Nagar - Thuban- Piprod- Chanderi - MP/UP Border near Rajgahtdam - Lalitpur - intersecting N-S corridor-Panari-Rajwara-Banpur(MP/UP boredr)-Tikamgarh intersecting NH-539 (Total length = 295; MP= 240; UP= 55)

55.009

Nagod- Kanijar- Narayani terminating at junction with NH- 35 between Banda and Chitrakut (Total length = 87 km; MP= 56 km; UP= 31 km)

31.0010

Stretch from Bareilly (junction at NH-30 near Civil Lines)- Bhutah -Bisalpur

36.0011

Stretch from Bewar (on NH-34) Fatehgarh-Miranpur Katra (on NH-30) Bisalpur (on NH-370)-Pillibhit on NH-730

191.0012

Stretch from Nawalpur-Ubhaon crossing- Sikandrapur-Maniar-Bansdih-Reoti-junction with NH-31

108.0013

Stretch from Allahabad -Koraon-Drumanodganj-Haliya-Awadhadam-Pipra-Manigarha- UP /MP border- Karondiya-Bagdara-Chatrangi-Singrauli extended up to junction on NH-39 in Madhya Pradesh near Waidhan (Total=176 km,U.P=104 km, M.P= 72km)

104.0014

Stretch from Karmaini (junction on NH-24 near Compierganj)-Menhdalwal Kahliabad- Dhanghata- Ramnagar- Nyori (junction on NH-28- Azamgarh

105.0015

Stretch form Agra (junction on NH-509 near Islam Nagar-Jalesar-Etah (junction on NH-34 near Police line)

79.0016

Stretch from Balia (junction on NH-31 nearTeekha )- Mau-Azamgarh on NH-28

100.0017

Stretch from Jaunpur to Khuthan extended upto NH-31 near Saidpur

60.0018

Stretch from Palia Shajahanpur via Hardoi -Lucknow

270.0019

Stretch from Mathura (NH-44) Hathras-Badaun-Bareilly (NH-30)

215.0020

Stretch from Moradabad- UP / Uttrakhand border- Jaspur-Kashipur (Total=58km,U.P=53km, Uttarakhand=5km,)

53.0021

Saidpur- Sadat- Jakhania- Jalalabad mor- Mardah

50.0022

Tarighat- Bara- Buxar(Uttarpradesh= 38.20 km; Bihar=10.80 Km)

38.2023

Akbarpur-Baskhari

23.0024

Muzzafarnagar-Jansath-Miranpur on NH 34

40.0025

Khurja on NH 34-Jewar

34.0026

Meerut-Garhmukteshwar (junction at NH 9)

47.0027

Sikandarpur-Ballia

35.0028

Jalesar-junction with NH 34 near Sinkandara Rao

25.0029

Gorakhpur (junction at NH 27)-Paratawal

32.0030

Maharajganj-Nichlaul-Thuthibari road (upto Nepal border)

39.0031

Basti-Mehdawal-Kaptanganj

92.0032

Faizalnagar-Tamkuhi-extended upto Salempur on NH 727A

52.0033

Salemgarh-Sewarhi-Padrauna

49.0034

Zamania-Gehmar

21.0035

Tamkuhira (NH 28)-Betia (NH 28B)

36.00

Total

2591.20