Project cost worth Rs 2300 crore
IRB Infrastructure Developers announced that the Company has emerged as a selected bidder and received Letter of Award from NHAI for the project of Four Laning of Kaithal - Rajasthan Border Section of NH-152/65 from km 33.250 to km 241.580 (Design Length 166 km) in the State of Haryana to be executed as BOT (Toll) on DBFOT Pattern under NHDP Phase - IV (the Project).Key highlights of the Project are as under:
- The Project is on DBFOT Pattern
- The estimated project cost of the Company is approximately Rs 2300 crore;
- The concession period for the same is 27 years;
- Construction period is 910 days.
More From This Section
- IRB has sought Rs 234 crore Viability Gap Funding from NHAI
- With this Project, IRB expands its base in 7th state viz. Haryana