The scope for Package No. 2 includes under-ground structures (tunnels & stations) 2.76 Km (approx.) long from Vellara Junction station to Shivajinagar station and three UG Metro Stations at Vellara Junction, M. G. Road and Shivajinagar on the Reach-6 line.
Package no. 3 involves design Et construction of under-ground structures (tunnels & stations) 2.884 Km (approx.) long from Shivajinagar Station to Tannery Road Station and two UG Metro Stations at Cantonment and Pottery Town on the same metro rail line.
The project is to be completed in 42 months.