Don’t miss the latest developments in business and finance.

NHPC declares commercial operations of Unit No. #2 of Teesta Low Dam HE Project Stage -IV

Image
Capital Market
Last Updated : Mar 30 2016 | 10:13 PM IST

On 31 March 2016

NHPC announced that upon successful trial run of Unit No. # 2 of Teesta Low Dam HE Project, Stage-IV (4 X 40 MW) at its installed capacity of 40 MW for continuous 12 hours on dated 29 March 2016, the Unit No. #2 is hereby declared under Commercial Operation w.e.f. 00:00 hours of 31 March 2016.

Further the Company has informed that, 100% Power generated from TLDP-IV has been allocated to the state of West Bengal and the same shall be supplied through West Bengal State Electricity Distribution Company (WBSEDCL).

Powered by Capital Market - Live News

More From This Section

First Published: Mar 30 2016 | 9:55 PM IST