At estimated cost of Rs 10598.98 crore

NTPC has accorded investment approval for Telangana Super Thermal Power Project, Phase-1 (2x800 MW) at current estimated cost of Rs. 10,598.98 crore. PPAs have been signed with Southern Power Distribution Company of Telangana and Northern Power Distribution Company of Telangana. The Commercial Operation Date (CoD) of first unit is envisaged in 52 months and second unit at an interval of 6 months thereafter.