(in cr.)
Physical Progress (%)1 Construction of KaralPhata Interchange from Km 3.600 to Km 6.073 of NH-4B & from Km 5.300 to Km 7.422 of NH-348 (old SH-54) and connectivity to proposed 4th Terminal of JNPT on EPC mode. (Package - I) 539 28.752 Construction of Gavan Phata Interchange from Km 14.740 to Km 15.894 of NH-4B, Km 13.160 to Km 14.880 of NH-348 (old SH-54) & Km 5.360 to Km 6.785 of Amra Marg and NH-4B (Km 6.073 to Km 14.740 and Km 15.894 to Km 21.200) on EPC mode. ( Package - II) 594.7 21.53 Construction of NH-348 (old SH-54) from Km 7.422 to Km 13.160 and Amra Marg from Km 0.000 to Km 5.360 on EPC mode (Package - III) 504 23.524 Construction of NH-4B from Km 21.200 to Km 27.270 and Km 0.000 to Km 4.492 on EPC mode. (Package - IV) 414 45As the road connectivity projects linking JNPT project length is less than 100 km, environmental clearance is not required for these projects.