After the project was declared a National Project, Ministry of Finance informed that it will provide 100% of the remaining cost of the irrigation component only, for the period starting from 01st April, 2014, to the extent of the cost of the irrigation component on that date. After this, CA of Rs. 3364.16 crore has been released for this project from 01st April, 2014 to 31st March, 2017. During 2017-18 CA of Rs. 979.36 crore has been released and another Rs. 1020.64 Cr. has been sanctioned.
The State Government has informed that they are taking all steps for timely completion of the project duly resolving all hurdles like pending land and R&R issues, finalization of designs, NH crossings, problems at work front etc. As informed by the Water Resource Department, Govt. of Andhra Pradesh, the project is targeted to be completed by 2019.
Powered by Capital Market - Live News