They said they were able to conduct inspection only for six days and requested further time to complete the entire inspection. They also said Assistant Executive Engineers and officials were also present during the inspection.
Advocate S Muthukumaran had filed a petition in 2011, stating that the municipal administration and water supply department had passed the G.O. On Jan 30 1997, restricting the height of the structures around the temple.
Devotees cannot see the temple towers from a distance, h further affecting their sentiments, he said.
S Ramesh and V Sitharanjandas, Advocate Commissioners, inspected the sites on various dates during the last month.
The report said they could not ascertain if most buildings were constructed before or after the G.O. Was issued.
They could not get plan approval of most buildings.