All issues regarding Navi Mumbai airport resolved: PM

Image
Press Trust of India Mumbai
Last Updated : Jan 10 2014 | 9:22 PM IST
Prime Minister Manmohan Singh today said all the pending issues related to the Navi Mumbai international airport -- which would provide a second airport to the metropolis -- had been sorted out, and the work was on.
"All the pending issues with regard to the Navi Mumbai airport have now been resolved and the Maharashtra government, in collaboration with the Central government, is now moving ahead on the work," Singh, who was here to inaugurate Mumbai airport's new terminal 'T2', said.
Navi Mumbai airport, conceived 27 years ago, has been held up due to issues relating to land acquisition and environment clearances.
After several months of negotiations, the project-affected persons (PAPs) have agreed to the Maharashtra government's offer of 22.5 per cent developed land for every hectare of land acquired.
The government has also agreed to provide one floor space index (FSI) for 12.5 per cent of the developed land and 2.5 FSI for another 10 per cent of developed land. Further, the PAPs would get three times more land to the current residential plot they occupy.
Of the 2,268 hectares required for the airport, 1,572 hectares are already acquired.
The project cost, estimated at Rs 4,766 crore in 1998, has risen to around Rs 14,573 crore as of date. The airport is expected to handle 60 million passengers annually.