The Government Accountability Office issued a report yesterday saying NASA's Space Launch System is at "high risk of missing" its planned December 2017 initial test flight.
The post-space shuttle program would build the biggest rockets ever, larger than the Saturn V rockets which sent men to the moon, to send astronauts to asteroids and Mars.
"They can't meet the date with the money they have," report author Cristina Chaplain said. She said it wasn't because the space agency had technical problems with the congressionally-required program, but that NASA didn't get enough money to carry out the massive undertaking.
NASA's launch system officials told the GAO that there was a 90 per cent chance of not hitting the launch date at this time.
Also Read
This usually means NASA has to delay its test launch date, get more money or be less ambitious about what it plans to do, said former NASA associate administrator Scott Pace, space policy director at George Washington University.
NASA is working on the problems GAO highlighted, but delaying launch or diverting money from other programs would harm taxpayers, NASA Associate Administrator William Gerstenmaier wrote in the agency's response.
The space agency has been reluctant to put an overall price tag on the Space Launch System. The GAO report says it will cost USD 12 billion to get to the first test launch and "potentially billions more to develop increasingly capable vehicles" that could be used for launches to asteroids and Mars.