"With this, 9 coal-based sets aggregating to 3,340 MW, all supplied and commissioned by Bhel, are now operational at Chandrapur STPP of Maharashtra State Power Generation Co. Ltd (MAHAGENCO)," Bhel said in press release.
The commissioned unit is the second 500 MW unit of Stage-III (2x500 MW) of the project being executed by Bhel.
Bhel has been a major partner in the power development programme of the state of Maharashtra.
The company has contributed more than 15,500 MW of generating capacity to the state, which is the highest capacity added by Bhel in a single state. It has supplied over 85 per cent of the coal-based sets installed by state utility.
Bhel had commissioned the first set of this project in March, 2015. Bhel-make 500 MW sets of this rating class today form the backbone of the Indian power sector and have been performing much above the national average as well as the international benchmarks.