"The company has now received all consents and approvals from the State Pollution Control Board, Odisha, for starting and operating the blast furnace No 2 installed at its steel plant," Bhushan Steel said in a BSE filing.
The state PCB in last November had directed closure of the blast furnace till further order, following an explosion that happened in the slag pit during the fourth day of trial run on November 10.
"The company has started the process of operation of blast furnace No 2 and the production from the furnace is expected to start in few weeks," Bhushan Steel said.