"The timeline for connecting 1 lakh GPs (gram panchayats) with OFC (optical fibre cable) to provide broadband connectivity under Phase 1 has been revised to December 31, 2016," Telecom Minister Ravi Shankar Prasad said in a written reply to Lok Sabha today.
Under the NOFN project, the NDA government had planned to connect 50,000 GPs by March 2015, another 1 lakh by March 2016 and rest of the one lakh by December 2016.
The government had approved NOFN project worth around Rs 20,100 crore in 2011 for facilitating at least 100 megabit per second (Mbps) bandwidth in all the estimated 2.5 lakh GPs.
The project is being handled by a special purpose vehicle under the Telecom Ministry which has distributed work to three central pubic sector units -- BSNL, Railtel and Powergrid.