"In this country, builders have developed an attitude to make committments to the purchasers and not fulfill them by delaying the projects," a bench headed by Justice Dipak Misra said.
The apex court's observation came after real estate firm Parsvnath Buildwell Pvt Ltd said it will give flats to 70 home buyers, who are before the court, by December 17.
"They (home buyers) do not have patience and trust in you and need refund. Money should go back to them and they should not suffer," the bench also comprising Justices Amitava Roy and A M Khanwilkar said.
Senior advocate Subramanian Prasad, appearing for the firm, said that as directed by the court, the company has deposited Rs 12 crore with the Supreme Court registry.
Also Read
The bench asked Supreme Court registry to disburse Rs 12 crore to the 70 home buyers on pro-rata basis after proper identification.
The court also noted the submission of advocate M L Lahoty, appearing for the home buyers, that the principal amount was Rs 22 crore and not Rs 15 crore as the impression was given on the last date of hearing.
Prasad said if refund is given to the 70 flat buyers, then over 800 home buyers will come seeking refund from the developers which do not have money.
Lahoty contended that home buyers were interested in refund as over 95 per cent of the money was paid to the developer in 2007 and they had committed to hand over the flats by 2011.
The apex court had on September 15 directed the firm to
It had asked the home buyers whether they would agree to the proposed deadline of December 2017 given by the developer and the quantified monthly rent.
The firm had said if the Ghaziabad Development Authority (GDA) re-validated the relevant plan, the building can be completed by the end of December, 2017.
The bench refused to agree with the contention and said the present litigation had nothing to do with the re- validation of the plan submitted by the appellant to the Ghaziabad Development Authority.
The firm was asked by the apex consumer commission in May this year to refund the principal ammount in four weeks with 12 per cent interest, Rs 3 lakh as compensation and Rs 25,000 as litigation cost to 70 buyers who had booked flats in the Parsvnath Exotica project.
The 70 buyers who had approached the NCDRC had said they had booked flats in the project in 2007 which was to be completed by 2011, and the delay was of over five years. They said that in 2015, GDA had cancelled the approval for the project, which was not their fault.
Parsvnath Developers Ltd had moved the apex court against the apex consumer commission's order asking it to refund the money to 70 buyers along with interest.