The Comptroller and Auditor General highlighted negligible progress in setting up underground automated parking (UGAP), wasteful expenditure on consultancy fee, and irregularities marred contract management at the three MCDs.
The report, covering the period from April 2010 to March 2015, was tabled in Delhi Assembly today.
A performance audit on 'parking facilities in MCD areas' revealed that 17 UGAPs were approved on PPP model in January 2007 but only one was created till July 2015. Part implementation of conventional multi level underground parkings (MLUGPs) resulted in "wasteful expenditure" of Rs 3.93 crore, it said.
"Failure of the Remunerative Project Cells (RP Cells) to ensure compliance of terms and conditions of agreement by licencees led to mismanagement of parking sites," it said.
Also Read
RP Cells of North, South and East Delhi Municipal Corporations are responsible for commercial utilisation of the parking sites.
The RP Cell of the then unified MCD identified 19 locations way back in 2005 for developing MLUGPs and the MCD approved plans for developing UGAPs at 17 of these locations but just one underground parking at Kamla Nagar was created as of July 31, 2015, said the report.
However, NDMC allowed licensees to continue running parking sites without the regular MLF payment and security deposit, resulting in "Rs 6.95 crore revenue loss", the report said.
The CAG found NDMC was allowing an "undue benefit" of Rs 2.57 crore to the licencee who was allotted terrace of the Parade Ground MLUGP at an MLF of Rs 4 lakh in April 2013 but the open area of the facility was also used till June 2015.