"While CEA (Central Electricity Authority) identified power generation capacity addition requirements of 67,439 MW for XIth plan period (2007-12) in the country in November 2003 itself, Bhel completed the first phase of its capacity addition programme in March 2011," Comptroller and Auditor General of India said in its report tabled in Parliament.
Thus, the manufacturing capacity expansion, which was required to be planned and completed in the initial years of the XIth plan was declared to have been completed by Bhel only towards the end of the plan, it said.
In addition to some uncontrollable factors, it said, delays due to reasons like non-fixation of targets for vendors to erect and commission machines, replacement of damaged equipment and delays in pre-ordering activities could have been minimised through improvements in market research, planning and monitoring.
"Existing installed manufacturing capacity for turbines, generators and boilers during 2007-11 remained largely under utilised," the report added.
More From This Section
There was considerable scope for improved utilisation. Though capacity utilisation picked up during 2011-12, there is a need to maintain and further improve it in order to achieve the benefits of ongoing capacity augmentation.
CAG Audit report examined the adequacy and results of efforts of Bhel from conceptualisation to execution of manufacturing capacity expansion and its utilisation during 2007-12.