In its performance audit report, the Comptroller and Auditor General of India said it has found that despite considerable progress in setting up institutions and creating funding arrangements, there are critical gaps in the preparedness level for various disasters.
"The NDMA, which was conceived as the apex planning and supervising body, was found ineffective in its functioning in most of the core areas.
"It neither had information and control over the progress of work at the state level nor was it successful in implementation of various projects," the CAG said in its report tabled in Parliament.
It said the system which came into effect in preparedness level for various disasters after the Disaster Management Act 2005 was yet to achieve its desired impact.
More From This Section
The CAG said the National Executive Committee had not met after May 2008, although the country faced many disasters since then and this had affected the evaluation of the disaster preparedness at all levels of government.
The CAG said the performance of NDMA in terms of project implementation had been abysmal. So far, no major project taken up by NDMA had seen completion.
"In many cases, NDMA realised midway that some other agency was already executing projects with similar objectives," it said.