Last week, Central Electricity Regulatory Commission (CERC) allowed higher tariff as well as a compensation of Rs 329.45 crore for the private utility's 4,000-MW project in Gujarat operated by its unit Coastal Gujarat Power Ltd (CGPL).
The watchdog has ruled for a compensatory tariff of Rs 0.524 per kWh for the project from the period beyond April 1, 2013, which has to be borne by Maharashtra, Rajasthan, Gujarat, Haryana and Punjab, the States which are procuring electricity from the imported coal-based plant.
As per ICRA, post-order the average consumer tariff rate charged by the utilities in these states is expected to rise in the range of 0.4%-1.8% or 3-10 paisa per unit.
In a separate order, CERC granted nearly Rs 830 crore compensation for Adani Power Ltd's (APL) 4,620 MW Mundra plant. Gujarat has to pay Rs 420.24 crore, while Haryana has to shell out Rs 409.51 crore as compensation from the commissioning date till March 31, 2013, the order said.
More From This Section
According to ICRA, average tariff for the utilities is estimated to increase by average 1.7 per cent or 7-10 paise per unit in Gujarat and Haryana.
Timely tariff revision or implementation of FPPCA (fuel and power purchase cost adjustment) framework remains extremely crucial for the distribution utilities, else it could affect their cash flow position, said ICRA.
"CERC's move is not only positive for APL and CGPL, but also for the generation sector as a whole."
Utilities in Haryana have already appealed to Appellate Tribunal of Electricity (ATE) against CERC's April 2013 for allowing compensatory framework, while those in Punjab have opposed tariff compensatory framework.