Net sales during the quarter expanded by 16.05 per cent to Rs 1,186 crore during the October-December 2013 quarter as against Rs 1,022 crore a year ago period.
"The average peak load factor during the quarter was up 1.8 per cent on year to 92.7 per cent, due to good demand during the quarter," CESC chairman Sanjiv Goenka told reporters here today.
The city-based power utility is looking to commission the second phase of 600 MW power plant at Chandrapur in Maharashtra by March. It also expects to commission the first phase of 600 MW Haldia power plant in West Bengal in October or November.
However, the rupee depreciation would see the cost of both the power projects going up and consequently and the power utility might have to raise its tariff during 2014-15 (April-March), he added.
More From This Section
"The impact would be more for the Haldia project. When we started, rupee was at 45-46 levels per dollar. Now with rupee hovering at around 63 (per dollar) levels the costs are going up," he said.
The 600 MW from the Haldia power project is expected to feed the Kolkata municipality region, where CESC is the sole distribution company.
Meanwhile, the company has signed a power purchase agreement with Tamil Nadu State Electricity Board for 100 MW of power which will come from the Chandrapur project, Goenka said.
"We are also in advanced talks with two other private sector discoms (distribution companies) for power purchase agreement for another 420 MW power from the Chandrapur plant," he added.
CESC was setting up a 10.6 MW solar power plant in Tamil Nadu, making it the second solar unit by the company. It already has a 9 MW solar power plant operating in Gujarat.
CESC planned to open three new stores in the hypermarket format by March, adding 71,000 sq ft of space.