After CBI prosecutor told the court that investigation officer (IO) would file the final report in the case within 10 days, Special CBI Judge Bharat Parashar asked the agency to file the progress report on its probe on April 7.
"Senior public prosecutor submits that the final approval of competent authority has since been received and IO shall be filing the report under section 173 CrPC within 10 days or so.
The court had earlier directed CBI to expeditiously submit the final report of its further probe into the case pertaining to allocation of Moira and Madhujore (North and South) coal blocks in West Bengal to VMPL.
The court was hearing a case allegedly involving VMPL and its officials in which they are accused of making false claims relating to land allocation to get undue advantage in the coal block allocation. The FIR was registered in September 2012.
CBI, however, had later filed a closure report saying that charges against VMPL or its directors or even against public servants could not be substantiated during the probe.