The Comptroller and Auditor General also found that no penalty was imposed by the Environment Ministry for violating conditions of environmental clearance in the last two years
The CAG report on 'Environmental Clearances and Post Clearance Monitoring' tabled in Parliament today also found that Regional Offices (ROs) had not been delegated powers to take action against the defaulting companies.
It also found "shortages" in compliance of 13 general conditions prescribed in the Environmental Clearances by the Project Proponents (PPs).
CAG sampled 216 projects which had been granted EC between calendar years 2011 to July 2015 to examine the process of grant of Terms of Reference (ToR) and ECs at the ministry and 352 projects which had been granted EC between 2008 to 2012 to check the post-EC monitoring.
Also Read
The CAG said that out of 216 projects only in 14 per cent of the projects the ToR was granted within the prescribed time limit of 60 days while in others there were delays upto 365 days.
"Cumulative impact studies before preparing the EIA reports was not made a mandatory requirement, thus the impact of a number of projects in a region on the ecosystem was not known," it said.
"There were delays at each stage of the EC process namely granting of Terms of Reference (ToR), scrutiny of final EIA Report, appraisal of the application by the Expert Appraisal Committee (EAC), placing recommendations of the EAC before the Competent Authority for a final decision and conveying recommendations of EAC and the decision of the Environment Ministry to the applicant," it observed.
CAG said in 56 per cent of the cases, approval of the
competent authority was not obtained for the actual number of trees cut by the Project Proponents (PPs) while groundwater was used without permission in 19 per cent of the cases.
"The annual environmental audit report was not submitted by PPs to State Pollution Control Boards in 19 per cent of the cases and in seven per cent of such cases construction or operations was commenced before grant of EC," it observed.
Construction of rainwater harvesting structures was not done in 29 per cent of the cases while shortfall in relief and rehabilitation measures for people affected by projects was observed in 22 per cent of the cases, it found.