"The company has successfully completed the project of rehabilitation and up-gradation of Mandla-Pindrai and Salimnabad-Vilayatkalan major district road intermediate laning/two-laning with paved/hard shoulder in the state of Madhya Pradesh on engineering procurement and construction (EPC) mode," Dilip Buildcon said in a BSE filing.
It further said: "The total project cost is Rs 190.80 crore...The company has completed the said project 185 days prior to the scheduled completion period and due to the earlier completion of the project, it is entitled to receive maximum allowable three per cent bonus of Rs 5.72 crore."