Earlier, Singh and Elias George, Managing Director of Kochi Metro Rail Limited commissioned an auxiliary/traction substation (ASS/TSS 1) at Muttom Metro Coach maintenance Depot.
KMRL officials said the 110 KV grid supply is expected to be ready by only in February.
"To facilitate the urgent need of traction power supply for the third rail at Muttom Depot test track, a temporary arrangement is made by availing 2 MW power from KSEBL.
In this process 11 KV grid at Muttom which is converted to 33 KV using 11/33 KV transformer and the 33 KV supply is fed to traction substation, stepped down and converted to 750 DC supply for energising the third track,"a release said here.
He was accompanied by Jitendra Thyagi, Director, Works, DMRC and A K Gupta, Electrical, DMRC.