The Bombay High Court today said that authorities are bound to follow due process of law even in the case of projects such as Metro if they affect citizens.
A bench of justices A S Oka and R I Chagla also said that anyone whose property is affected by projects such as Mumbai Metro is entitled to compensation.
The bench was hearing a plea filed by two residential societies from the city.
The petitioners said that the MMRDA, a state agency which is executing the Mumbai Metro project, has proposed realignment of the Metro II B line between D N Nagar and Mankhurd.
The new route passes through the two buildings, they said.
In March 2017, the MMRDA granted them No Objection Certificate for carrying out repair and redevelopment of the two buildings that house over 40 families, the petitioners said.
More From This Section
While the repair work is still on, the NOC expires on March 31. So they approached the MMRDA seeking an extension.
The MMRDA, however, informed them of the proposed realignment, and said the NOC will have to be reviewed as the buildings would come in way of a Metro line, they said.
This stand was illegal as only a year ago the MMRDA had permitted them to repair the buildings which were dilapidated and could prove dangerous for residents, the petitioners said.
"The MMRDA can't change its mind on a whim while our redevelopment work is on," the petitioners said.
The realignment should have been approved by the Union Government, they said.
MMRDA counsel G W Mattos said the agency had written to the Brihanmumbai Municipal Corporation, asking it to provide alternative accommodation to those affected by the Metro work.
The bench, however, asked whether the MMRDA had followed due process in proposing the realignment.
"Are you cutting through any part of this property or not? And if yes, then have you followed due process? After giving an NOC, can you change your mind a year later without even having followed due process?" the judges asked.
"If a resident is affected in any way by a project such as the Metro, then he or she will have to be compensated," the bench said.
It directed the MMRDA to decide on petitioners plea for review of the NOC within a week.