"We have begun the civil work for boiler of the first unit of 660MW for the second phase of Raghunathpur thermal power project," Raghunathpur power plant chief engineer Debashis Mitra told PTI.
He said this is just a beginning and it will take not less than two years to complete.
The development holds significance as DVC in November was planning to shift the project from West Bengal after officials were attacked by locals in protest.
The project got stuck and generation could not be commenced as DVC was not able progress with the 10 km water corridor pipeline for the plant due to law and order problem.
DVC has almost completed first unit of 600 MW for first phase 1200 MW (600MW x2) Raghunathpur project.