"The Union Minister for Surface Transport Nitin Gadkari will be visiting the site of the tunnel on July 13 to attend a function on reaching the breakthrough point of the tunnel," said, R P Singh, Director, National Highway Authority of India.
"We are holding a ceremony to celebrate reaching to the breakthrough point on the Chenani-Nashri tunnel as we have reached a point where both the ends of the tunnel meet inside the tunnel," Singh said.
He said they have reached the breakthough point in just 47 months which in itself is a first of its kind in the Himalayan region.
"It will take 10 or 11 more months to throw the tunnel open for traffic, as we have to carry out other works inside the tunnel" he said.
The work on the tunnel, costing Rs 2,518 crore, was started in May, 2012. The tunnel is part of the four-lanning north-south corridor project which involves construction of a 10.9 km-long highway, including two 9 km-long tunnels.