Line pipe orders for about 400-km for pipeline from Dobhi in Bihar to Durgapur in West Bengal has been placed, the company said in a statement.
With these awards, pipe supply orders for 2,100 km of the Jagdishpur-Haldia & Bokaro-Dhamra Natural Gas Pipeline (JHBDPL) project have been placed. Also, 1,700 km of line laying orders have been placed.
The prestigious 2,655 km long JHBDPL project, also known as the 'Pradhan Mantri Urja Ganga' project will originate at Jagdishpur in Uttar Pradesh, where main trunk pipeline from the west coast currently ends, to Haldia in West Bengal and Dhamra in Odisha.
"GAIL till date has committed over Rs 6,500 crore for the project," the statement said.
Also Read
The project, it said, will usher Industrial development in East India by supplying environmentally clean natural gas to fertiliser and power plant, refineries, steel plants and other industries.
The project will also provide clean energy to households and transportation in the cities en-route the pipeline.
GAIL said city gas network, laying activity in Varanasi and Bhubaneswar, has already commenced and the same in other cities like Patna, Ranchi, Jamshedpur, Cuttack and Kolkata will start by next month.
GAIL Chairman and Managing Director B C Tripathi said the company is committed to complete the project well within scheduled time and cost.
The project will cost Rs 12,940 crore and is targeted to be completed by 2019.