In a report presented in Parliament, the standing committee on Urban Development said that to decongest the Parliament house, a new annexe - an extension of the old one - is under construction in Parliament complex.
"The committee finds the work of extension of parliament house annexe building at Parliament house, amounting of Rs 261.86 crores, has been stopped because of scarcity of adequate funds," the report said.
The committee said it found that the Urban Development ministry had repeatedly asked the Finance ministry to allocate more funds.
The panel expressed anguish that the ministry had scaled down its demand from Rs 121 crore to Rs 73 crore.
"The committee, hence, strongly recommends for providing adequate budgetary allocation for completion of Parliament house annexe building at the earliest so that the work does not stop and is completed within a given time frame," the panel said.