"... The Corporation could add only 500 MW i.E. 11 per cent of the target of 4,700 MW (own projects) with a shortfall of 4,200 MW," said Comptroller and Auditor General of India report on capacity addition in power generation during 2007-12 by DVC which was tabled in the Parliament.
The report further said that the PSU planned to add power generation capacity of 6,250 MW during XI Plan period (4,700 MW by the Corporation alone and 1,550 MW through Joint venture).
It further said that with regard to Mejia thermal power station unit 5 and 6, Detailed Project Report(DPR) was prepared without adequate investigation and deficiencies were noticed after finalisation of orders which resulted in delay.
"... And in Chandrapura Thermal Power Station(CTPS) Unit 7 & 8, the execution work initially suffered for 26 months due to delay in handing over the land to the contractor, non-availability of storage space for shipment of materials at site, local law and order problems, abnormal rise in price of steel and cement etc," it said.
Also Read
"As per the manual of the Corporation, a contract should be awarded within 161 days from the date of invitation of tender. Out of 13 contracts, seven contracts were finalised with delays ranging from 12 to 117 days. Further, in respect of four contracts the delays were more than 100 days," it said.
The main reasons for delay were extension of bid submission dates and discrepancies in scope of work detected during finalisation of price bids, it added.