The company, Shapoorji Pallonji & Co Ltd (SPCL), built the Subrata Roy Sahara Stadium (now called Maharashtra Cricket Association Stadium) at Gahunje on Pune's outskirts.
A single bench of Justice Amjad Sayed last week directed the MCA to furnish the bank guarantee for an amount of Rs 150 crore in favour of the high court registrar.
Justice Sayed was hearing an application filed by MCA challenging an order passed by a Pune court on January 20 this year, directing the cricket body to deposit Rs 172.32 crore in any nationalised bank, in an account of joint names of MCA and SPCL, pending hearing of the case.
The Pune court had allowed an application filed by SPCL under the Arbitration Act seeking payment of the outstanding dues.
More From This Section
In February 2010, the MCA had issued a work tender to SPCL and a contract agreement was drawn upon.
The project manager, however, certified and approved the final bill for an amount of Rs 225 crore and also recommended that Rs 3.31 crore be witheld from the final bill on account of certain works in the stadium which have not allegedly been executed by SPCL.
In January 2015, the MCA informed the SPCL that it was unable to make payment as the same is subject to funding from the BCCI, which had not been able to release funds since it could not hold its annual general meeting as it had been stopped by the Supreme Court.
The SPCL, in its application before the Pune court, claimed an amount of Rs 172.32 crore, which includes the pending dues and an interest at 18 per cent per annum.
MCA's counsel Vineet Naik argued that the work of the stadium was to be completed by April 2011. However, the SPCL could not complete it on time.
"The completion of the project in the stipulated time period was the essence of the contract. Upon completion of the project and work of the stadium, the MCA was to get an amount of Rs 207.95 crore towards naming rights from Sahara Adventure Sports Limited," Naik said.
"The MCA could not get the amount from Sahara and arbitration proceedings for the same are on," Naik said.
After hearing the arguments, the high court noted that the MCA had recently availed a loan of Rs 107.96 crore from a consortium of banks. The MCA has also sought fresh funding to which the banks have agreed.
"Considering the facts of the case and looking at the conduct of MCA in having agreed to clear the dues of SPCL and thereafter raising belated claim for damages only reflects the intention of MCA to delay and obstruct the payment of dues to SPCL," Justice Sayed said in a 30-page judgement last week.
The high court also that the SPCL's interest is required to be protected till the dispute is adjudicated in arbitration.