"We direct the MMRCL not to carry out any construction activity or ancillary work pertaining to the Metro-3 project from 10 pm to 6 am for a period of two weeks," a division bench of Chief Justice Manjula Chellur and Justice N M Jamdar said.
The direction came on a petition filed by lawyer Robin Jaisinghani, a resident of south Mumbai, claiming that the authorities carried out construction activities through the night, causing inconvenience to all residents.
To this, Jaishingani claimed the concrete filling was being done by trucks which was causing noise.
"The Noise Pollution Rules and judgements of the high court clearly state that no noise emitting activity should be carried out between 10 pm and 6 am," Jaisinghani said.
More From This Section
The court said it would also want to hear the side of Maharashtra Pollution Control Board on the issue.
The construction for the 33-km Colaba-Bandra-SEEPZ Metro line-3 project is currently going on in Mumbai.
The project is a part of the Metro system which will connect the Cuffe Parade business district in south Mumbai to SEEPZ in the city's north-central suburb.